POC in CATS

Former Member
0 Kudos

Hi,

Here is a scenario, like we need to see the POC for the consigned activities through CATS. Can any body help out please?

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Use mesurement method "Degree of Processing" to calculate the actual POC. Assign this measurement method in "Progress" tab of the activity.

Refer below link for more information the "Degree of Processing"

http://help.sap.com/saphelp_47x200/helpdata/en/b4/ba853488601e33e10000009b38f83b/frameset.htm

Example:

If the work in a activity is 100hrs and u post 10hrs confirmation thru CATS system will show actual POC for the activity as 10%.

U need to run CNE1, to calculate the POC after posting the CATS entry to PS.

In CNE5 u can see the Project POC.

Venkat

Former Member
0 Kudos

Hi Venkat,

Thank u for the input,but requirement is like, Completion % is in need in CAT it self, and whatever the actuals we enter in CATs againist to Planned Hrs, it has pickup the values automaticlly in either in CAT2 or CAT5

Thanks in Advance.

Regards,