Plan-Driven in classic scenario

Former Member
0 Kudos

Hi there.

We are working with classic scenario in SRM 5.5

We are customizing plan-driven procurement (only MRP without PS and PM modules)

Is it possible the next flow?

For ECC system

1. MRP creates purchase requisition

2. We pass the purchase requisition from ECC to SRM as SC

For SRM system.

3. We create bid invitation and bids from the SC

4. We create a PO in classic scenario (in ECC)

We try to do it, but when the SC is created in SRM, always appears as extended scenario.

Moreover we have deactivated the extended scenario.

Is it possible to run Plan-Driven in classic scenario or it is mandatory extended scenario?

Thanks and regards.

Raúl.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

The document flow you mentioned is possible with classic scenario.(The SPRO setting "activate Extended Classic " is not checked).

You can have all PR's transferred form R/3 to SRM and create Bid invitations from the SC's created in SRM in Sourcing Application.

BR,

Disha.