How I assigning person responsable project to WBS
Thank you in advance
Hi,
please follow the steps below :
IMG ->Project System -> Structures ->Operative Structures -> Work
Breakdown Structure (WBS)-> Specify Persons Responsible for WBS
Elements. Click on new entries, create a person responsible number and give description to that and click on save.
go to T-Code: CJ20n -> open your project -> go to person responsible field -> click on radio button select the person responsible and save the project.
Thanks,
Dhruv Kumar Malhotra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Maintain person responsible in OPS6 and then assign it in CJ20N
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.