receipts or requirements date

Former Member
0 Kudos

Dear all,

I have created PIRs for the month of November, 2008. But the system is proposing the procurement proposals date as 31st October 2008. I want the proposals to be on 1st Nov 2008. Where I am going wrong?

Thanks and Regards,

Raghu

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

May be your bucket is monthly thats why it is creating receipt in the end of previous bucket.

Make it weekly if possible.

Also if you are using CTM engine , check setting in /sapapo/ctmcust

Aggregate Objects :

Demand Date :

Receipt Date : ( make as late as possible )

Manish

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Raghu.

Check the goods receipt processing time.

Rgds, M.

Former Member
0 Kudos

Hi,

there is no GR time

rgds

nitin_thatte
Contributor
0 Kudos

Hi

Please check bucket offset in T-lane (& Optimiser profile if you are using optimiser)

If you keep this value as zero, system will show same PR on 1st Nov 00.00 hrs. But if you keep it as 1.0, it will show receipt on 31st October 2359hrs.

Regards,

Nitin Thatte