on 10-22-2008 8:32 AM
HI SAP Gurus,
Can anybody explain what does mean Agreement status in the Rebate agreements?
Here i am able to see 4 status.
What is the difference between B Agreement released for settelmet and D Final settelment of agreement already carried out?
Thanks
hi,
The status can indicate whether a rebate agreement has been released for final settlement or whether a credit memo has already been created due to final settlement.
Status B indicate that agreement has bee released for settlment. this you do in change rebate mode.
Status D indicate that final agreement has been release for further process to create credit memo
Rgards
San
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think the status' are self explanatory.
B - Settlement still not taken place but has been released for you to settle.
D - Final settlement carried out and you cannot change any parameters in the agreement and more.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Rao,
Please refer link:
http://www.erpgenie.com/publications/saptips/052005.pdf
Specifiaclly to yuoe query, related to Agreement Status and Differences between B and D, read Pages 28 & 29.
Hope, his may help you.
Best Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.