Table containing Budget for a given project

Former Member
0 Kudos

Hi Gurus,

I have a requirement to fetch the ROOT LEVEL Budget FOR a given Project.

Can someone Throw some light on the tables involved and how they are linked.

Thanks in Advance

Deepak

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Check table BPGE with value Type(WRTTP) 41 for overall & 45 for Release budget

Venkat

Former Member
0 Kudos

Check Tables BPJA and BPJE.for Budget

you will have to find OBJNR number relevant to WBS element.

Rgds,

Nitin

Former Member
0 Kudos

Hi Nitin

I am a technical consultant..i am new to PS

Could you please let me know where will i find the OBJNR number for WBS element..

regards,

Deepak

Former Member
0 Kudos

Go to tabel PRPS..you will get the OBJNR number

Regards,

Nitin

Former Member
0 Kudos

I am supposed to fetch Current Budget field in the transaction CJ30 for a given Project.

I didnot find appropriate field in RPSCO for this.

please let me know if there is any.

Regards

Deepak

Former Member
0 Kudos

Table: RPSCO

Budget Type (Vorga): KBUD for original, KBR0 for return, KBN0 for suppleme