Unit of measure for calculation type C must be completed

Former Member
0 Kudos

Hi All

When releasing some contracts in SRM , we are getting the error message as above.

The error message doesn't specify any particular part and the contract has more than 3000 parts.

There are no conditions at header or item level.

There is no Target quantity also. Just a Target value for the contract and prices for individual items are maintained.

We are using extended classic scenario and the contract is manually created in SRM.

I have checked the OSS notes for this error, but they are mostly for contract creation in Bidding and not for a manually created SRM contract.

We checked the UOMs for all the contract parts with the UOMs ( Base and Purchasing) in ECC Material Master and they are OK.

In our scenario , MM changes in ECC are replicated to SRM in real time

Any pointers towards pin pointing the error will be rewarded!

Regards

Kedar

Accepted Solutions (1)

Accepted Solutions (1)

former_member183819
Active Contributor
0 Kudos

Hi Kedar

I too have the same problem.

SRM 550 SP15.

Miuthu

Former Member
0 Kudos

Muthu,

This problem was happening long back.

Thanks for finding that note though!

Regards

Kedar

former_member183819
Active Contributor
0 Kudos

hi kedar

that note is available for sp12 . still debugging with technical resource.

no clues.

muthu

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi,

We encountered this error message and resolved the problem by applying the following 3 SAP Notes:

a)     Note #1022928 - Unit of Measure for Calculation Type C Must Be Completed

        (Previously Mentioned)

b)     Note #1702484 - Unit of Measure for Calculation Type C Must Be Completed

c)     Note #1517648 - Default Conditions Added for Product Category Item Type

Although the contract required is similar to a "Limit" item, but had to be placed for bid, then the RFX PS Item Type was set to "Service" to receive the bid responses.  After accepting the bid response, then we created a contract from the bid response.  Since it was to be a "Limit" type contract, then we immediately removed the data from the following fields:

  1. Remove the Quantity
  2. Remove the Unit of Measure
  3. Remove the Price
  4. Remove the Price Condition

After removing the values from these fields, then we switched the PS Item Type from "Service" to "Product Category".  We added the Guaranteed Minimum and account assignment data to encumber the funds.  We were able to "Release" the contract successfully.

Bob Zinsmeister

Former Member
0 Kudos

Hi Guys

any conclusion on this toppic ??

I also get this error, but don't know what to do about it.

Jakob Bang

Former Member
0 Kudos

Hi Muthu

Did you get any clue about this error?

Former Member
0 Kudos

Muthu

I am again getting this error and strangely no item is pointed out.

former_member183819
Active Contributor
0 Kudos

aha.

point 1 :- material might be changed to anothe rmaterial group in ECC but GOA shows as old product category

point 2:- PO might have released against this GOA

Point3 :- you get the above error while revising the GOA

am i right?

muthu

former_member183819
Active Contributor
0 Kudos

Hi kedar

what about this note

Note 1022928 - Unit of measure for calculation type C must be completed

BR

Muthu