on 10-21-2008 11:01 AM
Dear SAPPER!
Please tell me How can I stop the creation of the release orders when the quntity is fully referenced from the Quantity contracts (CQ).
The order created with reference to OR.
Contract : Material :T0001 is 1000 Quantities
Order I have given 1000 Qty.
But still when I can create order only warning message is apperaing How can I change this to error message sothat the system stops allowing creation of orders.
Regards,
A S
GOTO OVAH, select the message number and change from warning to error towards the right side.
Sam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check the Completion Rule in the Item Category KMN and put it as C.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.