when we go for HB, MRP, system calculate PR qty as under:
PR qty= max. stock-avl.stockopen POatyopen PRqty-reservation
but it should calculate as under:
Pr qty= (max.stock-safety stock)(ROP-avl.stock)open POaty+open PRqty-reservation
How to get calculation based on 2nd formula.
Hi,
SAP help says:
The reorder point should cover the average material requirements expected during the replenishment lead time.
The safety stock exists to cover both excess material consumption within the replenishment lead time and any additional requirements that may occur due to delivery delays. Therefore, the safety stock is included in the reorder level.
(http://help.sap.com/saphelp_47x200/helpdata/en/37/8bbbd26a8111d3b4ed0004ac160649/frameset.htm)
I don't think you could change this setting (via configuration).
Regards,
Csaba
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.