problems issueing goods to customer

hi mine is make to order production. i ve created a sales order for a material . with strategy 40 in mrp 3 view. they ran mrp for sales order.

a planned order was generated. and then production and goods receipt was done to the SL.after that when i am trying to do Vl01n

no schedule lines due for delivery up to selection date.its not allowing me to issue goods to the customer.i checked the mmbe transaction for materials.they are in sales order stock unrestricted use.

how to solve this.

replied

Hi there,

In a delivery, availability check is usually done at the storage loc level.

In an MTO scenario, goods are GR'ed into a specific storage loc.

So check what storage loc rule is assigned to the delivery type (SPRO --> Logictics Execution --> Shipping --> picking --> Define picking location --> Assign rule for picking location). for eg MALA for LF. MALA is shipping poijt / plant / storage conditons. ALso you have RETA, MARE & any other custom routine.

Then check in OVL3 what storaeg loc determination is maintained for the combination shipping point / plant / storage conditions.

In MMBE give that storage loc & do the availability check.

In our company MTO items are GR'ed into a specific storage loc. Check the same in your company.

Also in the sales order --> Item --> schedule lines you will find 2 dates. The material will be confirmed against the date in the 2nd line (that is the material availability date). Give that date in VL01N, shipping point, sales order to create delivery.

Regards,

Sivanand