i have a strategy plan of 4M and 6M.
I put the scheduling period in the MP as 60 days.
But when i schedule it it creates a call object after 4 months.
According to my understanding it should not create any MP since i have put the scheduling period as 60 days..
Please correct if i am wrong..
Hi,
when you start again or start in the cycle, despite the scheduling period, the system establishes that at least one date (either with the status "waiting" or "called up") is generated. Even if the status is less than the cycle used.
If you do not enter a scheduling period, the system ensures that at least one waiting release exists. planning.
Hope this helps.
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Ramesh,
Generation of maintenace call depends upon your maintenace cycle not on scheduling period. You mention scheduling period or not syatem will generate fisrt call if your scheduling period is more than call length it will show you next plan also.
Regards,
Kaushal Rai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
Scheduling period we are specifying is used for system to display the no of the calls for the days specified in the scheduling period,based on the Maintenance plan cycle.
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.