on 10-20-2008 12:32 PM
Hi QM Masters
My client wants the work centers for which the production order is confirmed is to be displayed in the 04 Inspection lot for that production order while result recording
How to do this?
Regards
Mohan
Hi,
you have facilty in results recording, Additional Info, there you have facilty to enter the work centre data.
but need to look with your t-chinal team.
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mohan,
Inspection lot against inspection type '04' is automatically generated when a Process/Production Order is comfirmed and Lot creation Date (In SAP - it represents thru Lot Created On date) is the Production order confirmation date and it always available in T-Code QA32, QA33, QA03 etc.
During Result Recording you get it by go to ...
Environment --> Inspection Lot --> Display Inspection Lot --> Next screen comes then click on icon 'Admin. Data' Then you will get the Lot created on Date & Time etc. this is basically Production order confirmation date & time too.
Please revert with comments.
Thanks
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.