Dear PS Gurus,
How the Investment Management (IM) integrates with Materials Management(MM).In which type of scenarios would it be happen? throw some light on this issue.For eg In Stock/transport/Warehouse Business.Let me know some inputs.Points will be rewarded soon for all thoughts.
Thanks,
Sanju.
Hi,
Suppose you have a scanario of production of steel plant.
this scanario will be divided in two phases
1-project phase
2-production phase
if you r in project phase then you have to procure material for project for this u have to create project ,wbs,budgeting then
u will create pr,po and grn for stock and after issuing material
mm cycle has done.
then at periodically,create AUC and at closing of project AUC to
Fixed asset.
regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
10 | |
10 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.