Hello Gurus,

I have two materials X and Y with a delivery done for a STO.

The delivery and PO is possible to view for one material X in MD04 t code for supplying plant delivery and deliverying plant PO is visible.

But the same delivery is not visible for material Y in supplying plant but PO is shown in delivery plant.

Please let me know what need to be check to display in supplying plant.

regards

suresh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

You can see the delivery in MD04, if requirement is transfered from STO to delivery.

This transfer of requirement is depends upon requirement type.

Determination Of Requirement Types Using Transaction

In the standard system, requirements types are determined according to a specific search strategy beginning with the material strategy group.

Strategy for Determining the Requirements Type

1. First, an attempt is made to find a requirements type using the strategy group in the material master.

2. If the strategy group has not been maintained, the system will determine it using the MRP group.

3. If the MRP group has not been defined, the system uses the material type instead of the MRP group when accessing the corresponding control tables.

4. If no requirements type is found here, the system assumes a special rule and attempts to find a requirements type with the aid of the item category and the MRP type.

5. If this is not possible, a last attempt is made to find a requirements type with the item category only.

6. If the last attempt fails, the system declares the transaction as not relevant for the availability check or transfer of requirements.

So Plaese maintain strategy group in material master MRP3 view or in configuration of MRP group parameters in following configuration.

SPRO>Production>Material Requirements Planning>MRP Groups>Carry Out Overall Maintenance of MRP Groups>Plant> Maintain -->Material group --> strategy group --> and maintain default planning stategy group.

After maintaining strategy group, you will find delivery in MD04.

Hope this will solve your problem.

Thanks and Regards,

Deepak.

Former Member
0 Kudos

Hi,

Check whether the delivery has been issued by the receiving plant or not, if it is not issued by receiving plant the stocks will be in Stock-in-Transit and that will not be shown in MD04/Current stock requirement list.

Hope it helps,

Regards,

Siddu CP

Former Member
0 Kudos

Hello,

PGI is not done in supplying plant but the delivery is not shown in MD04 t code.

regards

suresh