on 10-20-2008 5:24 AM
Dear All,
Ex: I have raised a PO for Imports with account assignment category "Q",during creation of purchase order the Exchage rate was 46.65 INR. when i'm doing Invoice MIRO the exchage rate is 48.85.The difference is going against WBS element.But now our company wants the difference in currency should be against cost center
Please can any one suggest how can i hit Exchage rate difference against cost center.
Regards
subhash
Hi
As you have maintained Account assignement category Q that is for Projects - WBS elements, so any difference is being posted to that WBS element only.
If you donot want to post to a WBS element , then you need to creataea substitution ule in FI so that these get posted into a Costs center.
Please get in touch with your FI consultant & an ABAPEr to include the Substitution logic
Thanks & Regards
Kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.