I want to know the step by step procedure to settle Prodution Order which is assigned to a WBS.
Please help.
Regards,
Vishal
Following the procudure for settlement of Prod Order.
1.KGI2 Overhead calculation
2.co8b Settlement co product
3. KKS2 Variance
4. KO88 ACTUAL SETTLEMENT
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
After creating production order first you have to confirm it(CO15)....now check actuals in cost estimation then it should be delivered(MB31).....then teco the order in CO02.
After these follow the steps given in above reply like KO88 etc.
Regards
Abhinay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.