Batch Specific UoM

I was trying to set up material quantity calculation. However when i go to the material master, additional data i am not able to see the "Propotion/Production" tab.

Did i miss something during config?

Regards

TOM

Former Member
Former Member replied

Hi Pintoo,

For Activation "Proportion/Production" tab you have to first Activate Batch Management tick either in Purchasing view or in Plant Data 1 view.After Maintaining Batch Management you will find that Proportion / Production Tab in Additional Data tab of Material Master.

Regards,

Dhaval