how to split production order among several work centers

Former Member
0 Kudos

Dear all,

Can anyone explain me how i can distribute a single production order among different work centers.For example i have a production order of printing job for 1000 quantity.i have four printersbut in routing i have defined only one.now i want the job to be distributed among all the printers.How can i achieve this?

Please guide

Regards

Prashant

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In workcenter capacity tab page select capacity field in bottom. System will show another screen. In this enter no.of individual capacity as 4.

In routing select the opn & double click. In this enter no. capacity splitting is 4. Make tick mark in required splitting.

Now run MRP. System will schedule all 4 printers.

Regards,

Dharma

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

You need to create this as a single work center with 5 Individual Capacities, and you can use the capacity leveling/dispatching option to allocate the right workcenter to the individual machine.

Please refer this thread also,

https://forums.sdn.sap.com/click.jspa?searchID=17600876&messageID=5764639

Regards,

R.Brahmankar