po change

sub contract po has been created, and po has been released and stock has been transferd 541 and now iam doing migo but before that i want to make changes in po i want to give 10 % over delivery tollarence how to do this

reply asap

replied

I am not sure if this is your problem or not - but there use to be a problem with ME29N that it would not allow you to cancel the strategy once the po printed (see sap note 493900 #12). You may want to try cancelling the strategy with ME28.