SOP -create plan in mc94

Hi

When i am creating a plan in MC94 the periods are displayed in weeks , how can i change to days or months

Thanks

sanka

Former Member
replied

Dear,

For SOP go to MC94 then header menu EDITPeriod splitTotal--Week select here as you want.

OR.

Please do the settings as defined below:

SPRO -


> Production ---> SOP ---> Set parameters for infor structure and key figures -


>Select Table " S076 ---> Double click -


> in the next screen Click on Planning Periods -


>Press F4 -


> and define here as month.

Regards,

R.Brahmankar

Edited by: R Brahmankar on Oct 17, 2008 1:22 PM