When i am creating a plan in MC94 the periods are displayed in weeks , how can i change to days or months
Thanks
sanka
Dear,
For SOP go to MC94 then header menu EDITPeriod splitTotal--Week select here as you want.
OR.
Please do the settings as defined below:
SPRO -
> Production ---> SOP ---> Set parameters for infor structure and key figures -
>Select Table " S076 ---> Double click -
> in the next screen Click on Planning Periods -
>Press F4 -
> and define here as month.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Oct 17, 2008 1:22 PM