Project cost planning

HI all,

I am new to SAP PS.

I want to do manual cost planning for my project. I did this with CJ40. Planned values can be seen in CN41 or drilldown report like S_ALR_87013532.

I am also using activities in my project. When I use activity, activity plan values are increasing my WBS plan values. but I dont want it to get increase. e.g I use internal activity and use workcenter. So this increases my wbs plan value.

As I want to use manual planning only thr CJ40, how can i restrict the activities plan values not aggregating in WBS plan values.

Also some times, cn41 and S_ALR_87013532 reports shows somewhat different values.

for the same project, S_ALR_87013532 is showing only WBS plan values but cn41 shows activities plan vaues aggregated to WBS.

Pls guide..

Thanks..

replied

go to OPSV and deselect the 2 check boxes for category 20.

If u want only for this project then set 'Do not determine planned cost'" in network header control tab under costing section.

Venkat

Edited by: VenkatSrinvas Konda on Oct 17, 2008 9:09 AM