Hi PP Experts,

Can anybody please tell difference between Standaed Available capacity, Available capacity & Pooled capacity.Please explain with giving simple example. Please helpout.

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

We assign the Standard available capacity at capacity header (capacity view)of Workcenter (CR02).

In the work centre - capacity header overview give the following data in std available capacity sub heading

start :08:00:00

Finish:12:00:00

break:00:00:00

Capacity utlization - 100

No of ind capacity = 1

Hence the capacity of 16 hrs is fixed for this WC. This your standard avilable capacity.

OP37 Maintain Available Capacity Version

You can use it as Normal available capacity or maxnium avilable capacity. The active version of available capacity is used as a basis for scheduling.

Pooled capacity is nothing but an available capacity that can be used by several work centers.

An example of a pooled capacity is a group of setup personnel who perform setups for many work centers.

Pooled capacity

A pooled capacity can be assigned to several work centers. It is created and edited independently of the work center. This is useful if, for instance, a group of employees works in several work centers.

Capacities can be entered and changed in work centers, but also independently. The system distinguishes between.

For working with CR11 ,I think first the pooled capacity should be included in SPRO.

Just check out in SPRO-Production -BAsic Data-Work center-Capacity Planning-Define Capacity categories

We assign this pooled capacity in the work centre creation in CR01,under capacity overview ,just below to the capacity category.

Hope clears to you.

Regards,

R.Brahmankar

rajesh_sutar2
Active Contributor
0 Kudos

Thanks to all.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Available capacity:

The capacity available for ur requirements.For an example 2 machines having capacity of producing 10 quantities each. That means the by using the available capacity u may produce 20 qntys per day.

U can view the available capacity for each work center through cm01. This will show the available capacity for every work center in hours or minutes.

Pooled capacity:

Pooled capacity is not only for a particular work center. It can be used by several work centers.

For an example, A group of maintenance labours will do the repair works in all the machines (work centers) in a company. They are not specific for a particular work center. Here these maintenance group is said to be the pooled capacity.

Former Member
0 Kudos

Available capacity = Operating time x number of individual capacities

Say stat of day is 07:30:00

Finish 17:00:00

Length of breaks 01:00:00

Working hr = 8.5

That means Operating time = 8.5 * 90 % = 7.65 Hr

Available capacity = 7.65 * 14 = 107.1 hr =6,426.00 min .

Here my No. of indiv. cap.= 14 and Capacity utilization is 90 % .

Pooled cap :

An available capacity that can be used by several work centers.

An example of a pooled capacity is a group of setup personnel who perform setups for many work centers.

Hope this helps