Dear all
I am facing a problem that i have already given the planning time fence in my material master as 3 days and During MRP run it was not making any changes in 3 days planning . Till now we were always increasing the Sales operation plans but rescently we faced this problem whereever we started reducing the SOP plans that changes are made in the planning fence time and schedule lines are getting changed.
Please help me out
Regards
Refer How planning time fnce works
http://help.sap.com/saphelp_470/helpdata/en/f4/7d30a944af11d182b40000e829fbfe/frameset.htm