Activity price flow

Hi,

I want to know the activity price flow at month end.

We do settlements at month end for production orders and internal orders etc.

After production order settlements we can able to know the produced quantity, consumed hours etc.

I want to know the flow like production order settlement, actual price calculation, after actual price calculation this figures should be plan for the next month like.

I am missing some activities in between.

please guide me with t codes and explanation.

Sateesh

Former Member
Former Member replied

Hi, You are in the right direction. After actual price calculation, you need to carry out revaluation. After this step, you need to continue with overhead calculation, WIP calculation, variance calculation, and lastly settlement. Trust this helps much and do encourage our efforts! Cheers!