Hi Gurus,
my scenariao is related with production order confirmation.
During confirmation for the order,quantities of the semi finish materials can be updated during production order confirmation.But I have to lock this quantities,so that none will be change the quantities during order confirmation.
Pl. deliver the details,
Regards
Devendra
Dear,
Please try with transction veraint in SHD0 Go to SHD0 transaction and give CO11N and try to create a screen varient.
http://theguruspeaksaboutsap.blogspot.com/2007/12/creation-of-variant-for-making.html SHD0
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Following user exits can be helpful for your case:
CONFPP01 PP order conf.: Determine customer specific default values
CONFPP02 PP order conf.: Customer specific input checks 1
CONFPP03 PP order conf.: Cust. specific check after op. selection
CONFPP04 PP order conf.: Customer specific input checks 2
CONFPP05 PP order conf.: Customer specific enhancements when saving
Write logic as - before saving Check if -
QTY of each component (semi-finished or row) entered in goods movment line itme = yield qty * component qty in production order component view line item
else
give error messege..
Hope this will help
Regards,
Ravi Thakkar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.