Hi All SAP Proffessionals,
Can anybody tell me what do we mean by Contracts/Scheduling Agreements?
Hi there,
In a contract you enter into an agreement with the customer that he will buy a specified quantity of goods from you in a year. Validity peeriod is usually for 1 year unless otherwise specifed.
They are of 2 types:
Quantity contracts: Customer will enter into an aghgrement that he will buy 10000 quantity of item A in 2008-2009 irrespective of the value.
Value contract: Customer will aggree that he will buy $10000 worth of items from you in 2009-2009 irrespective of the item he takes.
Scheduling aggrement: Customer will enter into an aggrement by which you ship 100 items of material A on 10th of every month or 1st week of every month. Validity peeriod is usually for 1 year unless otherwise specifed.
Pls refer http://help.sap.com/erp2005_ehp_03/helpdata/EN/70/a7853478616434e10000009b38f83b/frameset.htm
http://help.sap.com/erp2005_ehp_03/helpdata/EN/70/a7853478616434e10000009b38f83b/frameset.htm
for further info
Regards,
Sivanand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mahesh,
A contract is a type of outline purchase agreement against which release orders (releases) can be issued for agreed materials or services as and when required during a certain overall time-frame.
Contracts are of two types:
1. Quantity contracts - Use this type of contract if the total quantity to be ordered during the validity period of the contract is
known in advance.
2. Value contracts - Use this type of contract if the total value of all release orders issued against the contract is not to exceed a certain predefined value.
But a scheduling agreement is a form of outline purchase agreement under which materials are procured on predetermined dates within a certain time period. A scheduling agreement consists of a number of items, for each of which a procurement type is defined. The
The following are the procurement types:
- Standard
- Subcontracting
- Consignment
- Stock transfer
Delivery of the total quantity of material specified in a scheduling agreement item is spread over a certain period in a delivery schedule, consisting of lines indicating the individual quantities with their corresponding planned delivery dates.
Contracts and Scheduling Agreement transaction codes:
Transaction codes:
Contracts: ME31K to ME35K
Scheduling agreements: ME31L to ME35L.
Please award if helps!
Thanks!
preethi.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.