on 10-17-2008 5:14 AM
Please help me to find the process to assign N number of diffrent work schedules to N personal areas.
Thanks in advance.
Go to PE03
Give SCHKZ
ex. D WERKS
nnn1 &SCHKZ=WSn1
nnn2 &SCHKZ=WSn2
nnn3 &SCHKZ=WSn3
Best Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
check
table no V_001P_ALL useing SM30
in case of features
u can use the feature SCHZK as our team member adi said
the default value shd be the DWS for that PA
Edited by: Sikindar on Oct 17, 2008 9:48 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.