I create Overhead structure
Now, I want to define new Calculation Base, O/H rates, Accrual objects. Please help me how to do it
Thank in advance
Minh
Hi,
As you have defined the overhead structure, now you can define the accrual cost elements as per the requirement.
Then under Product Cost Planning, basic settings for material costing, there is Overhead. Here you can define the calculation base for overhead, also the percentage overhead rates etc.
As the overhead structure is applicable for controlling area and the above overhead settings are also made at controlling area level, the same will be applicable for concerned co area.
Hope this helps.
regards,
Mandar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, It is very simple but it will go for three pages to describe and I thought it better to give you the link which gives full details to your work simple. www.sap-topjobs.com/SpecialPP.samplepc.doc Trust this helps much and encourage us to share more! Cheers!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.