Hi,

I wanted to run the product cost estimate for the materials before starting the actual production process.

I am trying to run E73: Project Manufacturing Sales order processing BPP for Industrial Machinery and Components.

My final assembly is "E73-1000" (Inhouse Production).

BOM consists of "E73-1100" (External procurement) and "E73-1200" (Inhouse Production).

Material "E73-1200" has three components"

"E73-1210", "E73-1220", "E73-1230"

Material "E73-1210" has two components

"E73-1211" (Both Procurement types) , "E73-1212" (Inhouse production).

Material "E73-1220" is to be externally procured.

Material "E73-1230" has two components

"E73-1234" (External procurement) , "E73-1235" (External procurement)

My production order will be for "E73-1200". In the BPP, We created project stock for E73-1210,

E73-1220, E73-1222, E73-1230 through transaction MB1C using movement type "501". E73-1222 is an added component for "E73-1200"

At the time of costing run, I am getting the following errors:

No routing could be determined for material E73-1000 (Whether this would impact costing)

No routing could be determined for material E73-1212(Whether this would impact costing)

Material E73-1212 in plant 1000 has no BOM (This was to be used for "E73-1210" for which a MB1C was directly done. Then whether there is any need to cost E73-1212.)

Object was not costed

Cost component split costed with value of zero.

No routing could be determined for material E73-1210

Cost estimate for material E73-1212 contains errors -> Planned price (This was to be used for "E73-1210" for which a MB1C was directly done. Then whether there is any need to cost E73-1212.)

No routing could be determined for material E73-1230

I am relatively new to costing. If somebody can send the sequential steps for costing, that would really help.

Regards,

Satish