Progress analysis to measure work done for a project if WBS only

Hi All,

Is there any solution to measure work done (let say in %) for a project if we use only WBS element...as per business term in our company...we cannot use network activities.

Plz advice.

Cheers,

Nies

replied

Hi

Pls download Project progress pdf thru following site

http://help.sap.com/printdocu/core/Print46c/en/Data/htm/english.htm

There are different measurement methods which can be used to measure WBS progress. some of then are start-finish rule, time proportionality, milestone, estimate etc.

you need to maintain progress version and need to maintain SKFs, value catagories etc.

this document will give you idea about progress analysis.

best of luck...