DSPT status on activity

Former Member
0 Kudos

Hi,

When does DSPT status set on the activity? How to remove that status from the activity

Regards,

Laxminarsimha

Accepted Solutions (1)

Accepted Solutions (1)

nitin_patoliya
Active Contributor
0 Kudos

DSPT is System status sets when you Dispatch ....

Process that delete this status when you cancel Scheduling

Regards

Answers (1)

Answers (1)

Former Member
0 Kudos
Former Member
0 Kudos

Thanks Nitin and Venkat

how does the status is set on an activity from project system(CJ20N). can you tell me which Tcode is used to set/remove this status.

Regards,

Laxminarsimha

Former Member
0 Kudos

hi

in CM35 capacity leveling u can enter with overallprofile , plant ,workcenter ,capapcity category 002 and it u dispatch a particular activity then status is DSPT and if u press deallocate it would come back to the intial status . once u save activity with requirment mentioning work center then it would go to the pool requriemnts of the work center and when u dispatch the requirements shifts from pool requirements to schduled requirements against work center .....in capacity levling and deallocate it would reverse again ..

regards