cancel
Showing results for 
Search instead for 
Did you mean: 

Stock Transport Scheduling Agreement

Former Member
0 Kudos

Hello all,

I have created a stock transport scheduling agreement (ME37) from plant A to plant B.

I think I have everything ok in SPRO.

However when I go to VL10F and try to create delivery no data is found.

Can you tell me the steps to configure this? And what am I missing? Because no error message appear and if I create the same data but for a purchase order instead of sch. agreement I can do the delivery.

Thanks in advance,

RMC

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

I was missing the maintenance of schedule lines in ME38.

Now is working.

Thanks

0 Kudos

Hi Greetings

While creating delivery for STO, there should be sufficient stock in the supplying plant.

This may be the root cause for the issue reported.

Please check the same and revert back.

Gobinathan G

Former Member
0 Kudos

Stock is ok in the supllying plant. I have 200 M3 in scheduling agreement and stock is 9000 M3

0 Kudos

Hi

Can you please check the following and revert back.

1) Required settings are complete in the following menu

OLME --> Scheduling Agreement --> Set up Stock Transport Scheduling Agreement

2) Schedule line are maintained for the scheduling agreement

3) Delivery creation date in the input screen of VL10F is appropriate or Plank.

Gobinathan G