PR instead of Planned Order in CNMM

Dear Gurus,

I am doing project oriented procurement CNMM.

But the result is giving me PR even for finished material. Actually it should give planned order for the same.

What could be the problems?

Useful answers will be given full marks.

Thanks and Regards

replied

Hi ,

Ur procurement type in material master may be X - Both procurement types make it E- In-house production if ur making procurement thru CNMM.

If u run MRP thru MD51 on WBS then system will generate planned order for X procurement type material.

Rgds

Edited by: Shrikrishna Rasam on Oct 16, 2008 3:13 PM