mile stone billing & down payment

Former Member
0 Kudos

i want to configure mile stone billing and down payment i was configured in the sales order milestone billing is working and the downpayment amount is also comming after raising downpayment invoice it was showing errror document is blocked i was checked there is no block how to do this problem please specify. and also specify the whole process of milestone billing & downpayment process.

Regards,

Kishore.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Kishore

Milestones needs confirmation of an activities to invoice that milestone. Else the block will be there. You can manually release the block

Path -- VA02 (double click on item) Billing plan tab, block you can see 02 will be there. Remove it & save the sales order. Then bill it

Thanks

Deepu Pillai

Former Member
0 Kudos

i as checked in the sales order there is no block for that downpayment line for other milestones it is 02 that lines are blocked

Answers (1)

Answers (1)

Former Member
0 Kudos

not yet finalised