Hello guys again,
Is there some setting (in IMG I guess..) which allows wbs' cost budget to be controlled against, for example, MM purchase order but not MM purchase requisition ? And, of course, where is it ?
Thanks !
Laimonas
SPRO->PS->Cost->Budget->Define tolerance limits
Column TR Group controls this.
Delete and create new entry if reqd and run CJBN for changes to take effect in existing project
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks guys !
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi ,
for this in IMG for costs settings in PS in Budget u can view define tolerance limit ....
here you have avialability control activity group where you can select 01 for avalability control for PO only
regards
pushpa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can set this in ''Define Tolerance Limit'' under tolerance group. You can set tolerance group as '' Purchase Order '' or ''Purchase Requisition''.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.