Cost budget control against MM document

laimonas_bindokaitis3
Participant
0 Kudos

Hello guys again,

Is there some setting (in IMG I guess..) which allows wbs' cost budget to be controlled against, for example, MM purchase order but not MM purchase requisition ? And, of course, where is it ?

Thanks !

Laimonas

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

SPRO->PS->Cost->Budget->Define tolerance limits

Column TR Group controls this.

Delete and create new entry if reqd and run CJBN for changes to take effect in existing project

Regards

Answers (3)

Answers (3)

laimonas_bindokaitis3
Participant
0 Kudos

Thanks guys !

Former Member
0 Kudos

hi ,

for this in IMG for costs settings in PS in Budget u can view define tolerance limit ....

here you have avialability control activity group where you can select 01 for avalability control for PO only

regards

pushpa

Former Member
0 Kudos

Hi,

You can set this in ''Define Tolerance Limit'' under tolerance group. You can set tolerance group as '' Purchase Order '' or ''Purchase Requisition''.

Regards,