What are Value categories and how are they defined in the system and what should be the basis for maintaining the value categories.what is the part of PS consulatant in defining the value categories,?
Your responses are highly appreciated..
Regards
Vinayak.
You may like to see your cost against some categories like material, services, contract etc, not just by WBS wise. In such cases you have to assign cost elements or CE groups to different value categories. Accordingly you can see the cost against each value category.
Regards
Rao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Refer Note:676123. Should answere ur queries.
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Value category is grouping the Cost elements for reporting purpose.You can define value categories thru OPI1and assigne csot element to it thru OPI2.
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.