10-16-2008 11:43 AM
Hi,
quick question: it is known that project specific customizing needs to start with Z or with Y in order to avoid being overwritten in the next SAP version.
Is there any other letter I may use in order to start my own customizing or developments?
Thanks,
F
10-16-2008 11:44 AM
10-16-2008 11:44 AM
10-16-2008 11:44 AM
Hi,
You can use your own namespace, other than 'Z'r 'Y' for customer developents.
Thanks & Regards,
Navneeth K.
10-16-2008 11:47 AM
>
> Hi,
>
> You can use your own namespace, other than 'Z'r 'Y' for customer developents.
>
> Thanks & Regards,
> Navneeth K.
But you have to apply for it and get it approved first. Tip - get as short a one as possible... I'm using one with 8 characters...