Consuption of independent requirement in DM from PS

We have scenario like this -

Strategy - Planning with planning material MTO

2 materials, A and B. B is planning material and it is entrered in the material master of A as a planning material. material B have independent requirements.

The requirement for material A is created through PS and that comes in MD04 (for A) as order reservation. Now we want this order reservstion created for material A, consumes independent requirement of material B.