Hi PP Experts,

Can anybody help me.

I have work center say XYZ where I perform milling operation. I have 3 milling m/c say 001,002,003. I have operation quantity is 150 piece.I want to specify that 40 pieces are to be processed on machine 001, 60 pieces on machine 002 & 50 pieces on machine 003.

How I can allocate this.Please help out.If possible please tell step by step procedure.

replied

Hi,

In the Capacity header , with no. of individual capacities=3. Create header details for individual capacities from Goto -> Individual Capacties and maintain for 001, 002 and 003.

Now after creation of production order, in operation details, Choose "Cap. reqmt assignmt" tab and choose capacity 001 and assign 40 pcs, for 002 =60 pcs and 003=50 pcs in split qty as required.

After assignment, you can also level this capacity using CM27 (Levelling done by Splits).

Hope this helps for your requirement.

-Thaila Shree