Dear Gurus,
I am creating a stock transport order. When i create the Stock Transport Order (PO) against my PR generated from the MRP run, The supplying plant is not derived automatically. In material master special procurement is selected as 40 "Stock transfer (proc.from alter.plant)"
Can anyone please help me for it configuration?
Best Regards,
Farooq Rifai
HI,
You cannot create the STO from the PR genearted thro MRP as it shall not contain the Item category U.
Therefore please raise a new PO with the Item category as U, then u may get the supplying plant option.
Hope it helps.
Regards,
Prasanna
Award pls if helpful
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to ME01 (Maintain Source List), here in the selection screen, enter material and receiving plant and enter
Now maintain the validity period, Supplying Plant, Purchase Org. and MRP indicator as "1" and save.
Then try.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the quick reply.. yes it is working fine.
But it will be very help full if you can advise some other way (Customizing) to achieve the same. We already have some plants which are already being derived at the time of transfer order without using the source list...
Thank you once again