hi all

CAN anybosy explain me about the RELEASE INDICATOR in release strategy for PO and PR.

Please explain me step by step , how we can keep release indicator for 4 levels release .

Thanks

sap-mm

replied

1 Cannot be changed

If you set this Release Indicator You cannot Change the Purchase Order once it is Released. Whenever you try to Change the po in ME22N it will be in Display mode only and Throw Error Message Like PO is already Released, Changes Not Possible.

2 Changeable, no new determination of strategy

If you set this Release Indicator You can Change the Po after Release in ME22N and It wont Ask for New Release Strategy.

3 Changeable, new release in case of new strategy

If you set this Release Indicator You Can Change the PO after Release but Again it will be Subject to Release Strategy. You should release the same po again.

4 Changeable, new release in case of new strat. or val. change

5 Changeable, new release if new strategy/outputted

6 Changeable, new rel. if new strat. or value change/outputted

Changeable, new release in case of new strategy

If you set the above Release Indicators You can Change the PO after Release but Again it will be Subject to Release Strategy as per the Changeability Values Settings.