How can we schedule a background job for order TECO?

Dear Experts,

Our client needs to schedule a background job for Prd order TECO. Currently COHV is being used, but it has to be done after manual selection of orders. Is it possible that we run it automatically everyday as a batch job?

Thanks,

Sachin

Former Member
Former Member replied

Hi

IN COHV, select the parameters for background job like for an order type or plant etc. Then goto mass processing, select TECO, select background in execute fundtion option and create a variant and save.

In SM36 create job, enter the program PPIO_ENTRY,enter the variant created , schedule the date and time.