on 10-16-2008 8:33 AM
Dear Experts,
Our client needs to schedule a background job for Prd order TECO. Currently COHV is being used, but it has to be done after manual selection of orders. Is it possible that we run it automatically everyday as a batch job?
Thanks,
Sachin
Dear,
Yes. You can schedule in the background.
You can use transaction COHV, here in system status field select 'TECO' & then in mass process tab select 'Technically complete'.
Then goto progam in the menu bar & choose execute in background.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
IN COHV, select the parameters for background job like for an order type or plant etc. Then goto mass processing, select TECO, select background in execute fundtion option and create a variant and save.
In SM36 create job, enter the program PPIO_ENTRY,enter the variant created , schedule the date and time.
Hi,
Try with tcode CO44. With this you can do mass TECO by online. Enter the plant & select technicaly complete. Remove tick mark from test run.
Now all the prod order will get TECO status collectively.
Regards,
Dharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.