Hi all PP gurus,
Can you please help me out in this issue please? .
Suppose we are having one material no .XYZ.and This material is, also blocked for purchasing status 03, has no reordering point, no reservation, MRP type: ND (no material planning) AND anyhow it comes up on the MRP-run How come? Have you any idea??means suppose we check in MD04 then it is showing one PR.How?
Thanks ,
Narayan
Hi Narayan,
May be PR is created manually, or created earlier before materials is block for procurement and MRP.
Just check in MD05.It will saw last MRP result with date and time.
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Please run MRP again with planning mode-3 deleted and recreated and you can also do the consistency check for MRP. Then check your result.
Also check planning file entry in MD20
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.