MTO Scenario

Dear All,

I have one scenario. Finished material requirement totally depends on sales order. As sales order comes, design of the machine starts and design dept prepere BOMs for that specific sales order. Only 2% semifinished material is used in next sales orders. In this case in standard SAP,we have to create new material codes for each semifinished materials.

Is there any alternative to prevent creation of new material codes? It will reduce users efforts in creating every time new material codes and system load also.

Mayur

replied

HI,

if you have alot of product but still can be group into variant, some will use VC (Variant Configuration),

but if you don;t use VC then you have to create a lot of new material.

I hope it's help.

bets regards,

Freddy Ha