Subcontracting - Material temporarily comes back into Own Stock

Hello all,

My client has the following business process:

Raw Material is sent to the SC vendor for processing. SC Vendor does some processing and brings it back to the plant, say as SFG-1, for the partly processed material to be put to temperature treatment.

The SFG-1 that was brought in for treatment is taken back to SC Vendor's place as SFG-2. SC Vendor does further processing and provides the FG.

From my understanding, this is achievable using 2 Subcontracting POs and a Production Order for the temperature treatment. However, the client doesnot wish to break up the SC order and have it as one order, and at the same time, capture temperature treatment cost.

Request your suggestions on how to handle the situation. Thanks in advance.