PIR Conversion to Planned Order

Hi All,

I have run M R P through MD01. Planned independent requirement is of 800 units. Stock of material is 100 units then it is creating planned order of 700 units. While we want that planned order should be the same as Planned independent requirement i.e, 800 units no matter what is the stock of finished material, as we want to create production order for make to stock. How can I handle it?

Regards,

Hammad

replied

Dear,

If you change the strategy from 10 to 11 no areas will get affected.

This strategy is particularly useful if you need to produce, regardless of whether you have stock or not.

You need to maintain the following master data for the finished product:

Maintain strategy group 11 on the MRP screen.

Set the Mixed MRP indicator to 2 on the MRP screen.

Maintain the item category group (for example, NORM) on the Sales Organization screen.

Maintain the Availability check field so that you perform an availability check without the replenishment lead time (checking group 02 in the standard system).

Difference

Strategy 10 11

Stock is taken into account Yes No

Reduction of planned independent

requirements takes place during u2026 u2026 goods issue for ... goods receipt for a production

the delivery order

Hope clear to you.

Regards,

R.Brahmankar