PIR Conversion to Planned Order
Hi All,
I have run M R P through MD01. Planned independent requirement is of 800 units. Stock of material is 100 units then it is creating planned order of 700 units. While we want that planned order should be the same as Planned independent requirement i.e, 800 units no matter what is the stock of finished material, as we want to create production order for make to stock. How can I handle it?
Regards,
Hammad
R Brahmankar replied
Dear,
If you change the strategy from 10 to 11 no areas will get affected.
This strategy is particularly useful if you need to produce, regardless of whether you have stock or not.
You need to maintain the following master data for the finished product:
Maintain strategy group 11 on the MRP screen.
Set the Mixed MRP indicator to 2 on the MRP screen.
Maintain the item category group (for example, NORM) on the Sales Organization screen.
Maintain the Availability check field so that you perform an availability check without the replenishment lead time (checking group 02 in the standard system).
Difference
Strategy 10 11
Stock is taken into account Yes No
Reduction of planned independent
requirements takes place during u2026 u2026 goods issue for ... goods receipt for a production
the delivery order
Hope clear to you.
Regards,
R.Brahmankar