on 10-16-2008 12:55 AM
Hi Team.
I Have problem with the FM SWW_WI_ADMIN_COMPLETE.
In 4.6 version i don't have problems, the WF in process is complete and contin ue the flow in the Workflow.
But now we are upgrade to 6.0 Unicode system.
When I try use this function, The task is complete but the workflow is in error.
For project reasons I need use a FM so can be used in 4.6 and 6.0
Maybe I use in incorrect form the FM.
I Fill the next steps:
WI_ID = wf_id
DO_COMMIT = ' X '
RETURN_CODE = ' 0001'
USERID
In 4.6 it's right but not in 6.0
Anyone have any idea to solve this problem
You should post this in the workflow forum and not in this one. This one is for SRM related issues. You can find the workflow forum [here.|;
Regarding your problem, I don't think it is a problem with the Fm but with the workflow. Search here on SDN for a document on upgrading from 4.6C to ECC for workflow. There are some actions which should be performed I think.
Regards,
Martin