on 10-15-2008 8:33 PM
We are on SAP R/3 4.7. We are currently using Project system for customer projects. We are manually linking the WBS element to the sales order item.
We are considering to automatically creating project from sale order.
Can someone offer any suggestions or recommendations?
If you have already done in the past, did you encounter any issues or concerns that need to be considered?
Thank You
Sanjay
Hi,
You can use the Functionality '' Assembly Processing'' to create project from sales order.
Please refer:
http://help.sap.com/saphelp_470/helpdata/en/41/191f9a45fd11d188ff0000e8322f96/frameset.htm
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for your help. Can you please guide us in regards to configuration setting?
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
you can do it by assembly processing.
for which you have to do follow things
1-create materail master with assembly processing.
(u have to maintain Strategy group 83 or 85 in MRP3 tab).
2-create stander project and standerd network.
3-go to CN08 and assign standerd network & create stander project to ur materail master .
4-then create sales order with this material.
when you save the sales order project will automatiaclly created.
Hope this will help u.
Regards,
Vivek tripathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As per standard configuration:
1.) Maintain requirement class in OVZG as 80
2) Maintain Requirement type in OVZH as KP and assign 80 there
3) Strategy in SPRO->Project System->material->Strategy and maintain requirment class and requirement type and account assignment there.
4).Then maintain strategy in strategy group...it would be same as 85.
5). Then you can maintain item category from SD side and item category group from MM and assign these item categories to SD document type .
6). Now create standard templates(Project and network activities and make assignment to standard project)
7). Create configurable material(Variant configurator) in MM01 as KMAT and maintain item category group as same defined above and maintain strategy group in MRP tab same as defined above.
8). Now assign these Variant configurator to standard network and projects in CN08.
Look into these setting would definately help you.
Regards
Abhinay
Refer below Case study rather than online help...
https://www.sdn.sap.com/irj/sdn/wiki?path=/display/plm/assembly%2bprocessing%2bwith%2bsap%2bps
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
when you save the sales order, the project will be automatically created.
that's the assembly.
please check the assembly on ONLINE HELP.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.