on 10-15-2008 4:35 PM
Hi,
We are setting up invoicing plan in our system. Can anybody please help in following.
1. How can we setup invoicing date as 15th of every month. My client want to have the invoice generated on 15th.
2. For first 12 months amount should be 8000 and from 12 months it should be 7500.
We are using Periodic invoicing plans.
Thanks
TOM
Invoicing plan
1. You can create a Date determination rule for this at
SPRO> MM>Purchase Order -->Invoice plan -->Determine rules for date determination.
you should have an entry which says
base line data is agreement start date
time period is 1 month
use this date determination in your invoice plan under invoice date suggestions give the one which you have created above
or else you can change the dates on the invoice plan when u create the purchase order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Thanks for the reply..
Is there a way to make the invoice date automatically to 15th of every month.
Also how to setup the two values
1. For first 12 months amount should be 8000 and from 12 months it should be 7500.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
In order to work with an invoicing plan, you must maintain the following settings (among others) in Customizing:
Desired invoicing plan type
Date categories
Date descriptions
Date proposals
You can also specify whether the invoicing dates are to be entered/maintained manually or whether the system is to suggest them.
You can do settings here:
SPRO ---> MM --> Purchasing --> PO --> Invoicing plan --> see here all the settings...
Hope it helps...
Regards
Priyanka.P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi priyanka,
In my case , when i see the PO Item -> invoice Plan, Billing status indicator showing as C ( fully processed ) , but like to change the dates, so is it possible to bring back the indicator as A ( not processed yet ) and can it possible to change the dates ?
Thnx & Reg
Pavan Kulkarni
+91 9052391140
User | Count |
---|---|
97 | |
10 | |
10 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.