Production Order For Project with plant stock

Hi,

We have a scenario where in we are required to create a production order for a project.

But the material(raw material) is in a storage location and is a stock item. Even the header material is also a stock item and it to stored in the storage location.

But the order is to be created for Project and to be settled to the Project. Now the system is not allowing me to create the order.

The error is :

"Project does not allow make-to-order stock

Message no. CO746

Diagnosis

There is no project stock for the project.

To create a production order with reference to a WBS element the project must allow project stock to be maintained.

Procedure

You should select a project that allows project stock."

Now,

I don't want to have a project stock. How to go forward...

Regards

Pavan

Former Member

Helpful Answer